Director Memorandum 14-060
Date: July 16, 2014
Prepared By: Brent Anton, Engineering Manager
Subject: Authorization to Solicit Bids for the Construction of the 6.0 Million Gallon
Reservoir R-12.4 - Calimesa
Recommendation: That the Board of Directors authorizes the District staff to solicit
construction bids for the R-12.4 Reservoir Project.
The California Statewide Communities Development Authority developed the Statewide
Community Infrastructure Program (“SCIP”) to provide property owners with the ability to finance
development impact fees and construct facilities through an acquisition agreement that qualifies
under the 1913/1915 Act via tax-exempt bond issuance proceeds.
The Yucaipa Valley Water District
has been approached by several
property owners interested in
exploring this financing mechanism
for the construction of the 6.0 million
gallon drinking water reservoir in
Pressure Zone 12 (Reservoir R-12.4)
planned for construction on a graded
pad near Singleton Road in
Calimesa.
On February 25, 2014, the Board of
Directors conducted a public hearing
and adopted resolutions approving
the financing of Reservoir R-12.4
through the California Statewide
Communities Development Authority
using the Statewide Community
Infrastructure Program (“SCIP”).
Based on the attached schedule, the
District should stay ahead of the financing program to ensure there are sufficient funds to
construct the facilities prior to the sale of bonds. Therefore, it would be advantageous to authorize
the solicitation of construction bids for the reservoir project at this time.
Yucaipa
Yucaipa Valley Water District Board Meeting - July 16, 2014 - Page 93 of 95Valley Water District Board Meeting - July 16, 2014 - Page 93 of 95
Date: July 16, 2014
Prepared By: Brent Anton, Engineering Manager
Subject: Authorization to Solicit Bids for the Construction of the 6.0 Million Gallon
Reservoir R-12.4 - Calimesa
Recommendation: That the Board of Directors authorizes the District staff to solicit
construction bids for the R-12.4 Reservoir Project.
The California Statewide Communities Development Authority developed the Statewide
Community Infrastructure Program (“SCIP”) to provide property owners with the ability to finance
development impact fees and construct facilities through an acquisition agreement that qualifies
under the 1913/1915 Act via tax-exempt bond issuance proceeds.
The Yucaipa Valley Water District
has been approached by several
property owners interested in
exploring this financing mechanism
for the construction of the 6.0 million
gallon drinking water reservoir in
Pressure Zone 12 (Reservoir R-12.4)
planned for construction on a graded
pad near Singleton Road in
Calimesa.
On February 25, 2014, the Board of
Directors conducted a public hearing
and adopted resolutions approving
the financing of Reservoir R-12.4
through the California Statewide
Communities Development Authority
using the Statewide Community
Infrastructure Program (“SCIP”).
Based on the attached schedule, the
District should stay ahead of the financing program to ensure there are sufficient funds to
construct the facilities prior to the sale of bonds. Therefore, it would be advantageous to authorize
the solicitation of construction bids for the reservoir project at this time.