Page 145 - Yucaipa Valley Water District
P. 145
Director Memorandum 16-041



Date: April 20, 2016

Prepared By: Jack Nelson, Assistant General Manager

Subject: Notice of Completion for the Construction Contract with Dustin Smith
Equipment, DSE Grading and Demo for the Demotion of the Building,
Basement and Foundation at 35192 Cedar Street Avenue, Yucaipa

Recommendation: That the Board authorizes the filing of the Notice of Completion.


At the regular meeting on February 3, 2016, the Board awarded a construction contract to Dustin
Smith Equipment, DSE Grading and Demo for a sum not to exceed $19,900 for demotion of the
building, basement and foundation at 35192 Cedar Street Avenue, Yucaipa (APN 0303-232-17).
[Director Memorandum No. 16-012].

The project is now complete and there are no change orders. Therefore, staff recommends that
the Notice of Completion be filed for this project.

















































Yucaipa Valley Water District - April 20, 2016 - Page 143 of 158
   140   141   142   143   144   145   146   147   148   149   150