Director Memorandum 17-018
Date: February 7, 2017
Prepared By: Brent Anton, Engineering Manager
Subject: Notice of Completion for the Construction of a 6.0 Million Gallon R-12.4
Reservoir - Calimesa
Recommendation: That the Board authorizes the General Manager to file the Notice of
Completion for Gateway Pacific Contractors.
On November 19, 2014, the Board of Directors awarded a contract for the construction of the 6.0
million gallon R-12.4 drinking water reservoir to Gateway Pacific Contractors for a sum not to
exceed $7,520,080.00 [Director Memorandum No. 14-091].
The project is now complete and the District staff recommends that the Board authorize the filing
of the Notice of Completion and release of the retention amount of $376,004.00 thirty-five days
after the recorded date.