Director Tom Shalhoub - Yes

                   •  General Manager Joseph Zoba reported on the emergency                STAFF REPORT
                       pavement replacement bids that were received for roadway
                       repairs on Oak Mesa Drive and Wildwood Canyon Road due
                       to the water mainline leak on November 11, 2017.  Two bids
                       were  received:  JB  Paving  &  Engineering  in  the  amount  of
                       $51,550; and PacWest Engineering in the amount of $51,427.
                       The  District  staff  will  authorize  PacWest  Engineering  to
                       proceed  with  the  emergency  repairs  which  should  be
                       completed within the next two weeks.
                   •  Management Analyst Matthew Porras stated that he has been
                       working  with  the  contractor  awarded  the  steel  building
                       erection contract on October 3, 2017 in the amount $150,000.
                       The District staff is proposing to increase the functional area
                       of the building by an additional 2,000 square feet for a revised
                       cost of $208,075.  The District staff requested concurrence
                       from the Board of Directors to proceed with the understanding
                       that  documentation  will  be  resubmitted to  the  Board  at the
                       next board workshop.  There was a consensus from the board
                       members to proceed to keep the project on schedule.
                   •  General  Manager  Joseph  Zoba  requested  a  motion  for
                       discussion  of  an  emergency  issue  as  agenda  item  6.E.
                       regarding interior coating repairs of drinking water reservoir
                       R-17.1.1.  Director  Chris  Mann  moved  and  Director  Tom
                       Shalhoub seconded a motion to add emergency item 6.E. to
                       the agenda as a discussion item.

                       The motion was approved by the following vote:
                              Director Jay Bogh - Yes
                              Director Bruce Granlund - Absent
                              Director Lonni Granlund - Yes
                              Director Chris Mann - Yes
                              Director Tom Shalhoub - Yes


                                                                                      DISCUSSION ITEMS:


               Following  a  staff  presentation  by  Chief  Financial  Officer  Allison         DM 17-104
               Edmisten, Director Lonni Granlund moved and Director Chris Mann         PRESENTATION OF
               seconded a motion to receive and file the unaudited financial report.      THE UNAUDITED
                                                                                       FINANCIAL REPORT
               The motion was approved by the following vote:                            FOR THE PERIOD
                       Director Jay Bogh - Yes                                      ENDING ON OCTOBER
                       Director Bruce Granlund - Absent                                            31, 2017
                       Director Lonni Granlund - Yes
                       Director Chris Mann - Yes
                       Director Tom Shalhoub - Yes





               Yucaipa Valley Water District                                                        Page 2 of 5
                                    Yucaipa Valley Water District - December 5, 2017 - Page 5 of 33