Page 52 - Yucaipa Valley Water District
P. 52

Workshop Memorandum 18-013



                Date:          January 9, 2018

                From:          Joseph Zoba, General Manager

                Subject:       Overview of the Yucaipa Gateway Plaza Development


               The  Gateway  Plaza  Project  involves
               four  parcels  that  will  be  developed  to
               include  a  gas  station,  a  restaurant,  a
               fast food building, and a hotel

               The developer has recently obtained a
               building  permit  and  nearly  completed
               the  construction  of  the  gas  station
               located  near  the  intersection  of  14
                                                     th
               Street  and  Oak  Glen  Road.    The
               developer  intends  to  hire  a  private
               contractor  to  haul  and  dispose  of  the
               sewage  from  the  gas  station  and  car
               wash,  so  sewer  service  will  not  be
               required  initially.    The  developer
               acknowledges that the gas station and
               car  wash  will  be  connected  to  the
               District’s  sewer  system  when  the  lift
               station is completed.

               The District staff is working the developer to create a development agreement that would eliminate
               the proposed lift station.  The main points of the development agreement will be reviewed at the
               board workshop.





























                                    Yucaipa Valley Water District - January 9, 2018 - Page 51 of 175
   47   48   49   50   51   52   53   54   55   56   57