Workshop Memorandum 18-013
Date: January 9, 2018
From: Joseph Zoba, General Manager
Subject: Overview of the Yucaipa Gateway Plaza Development
The Gateway Plaza Project involves
four parcels that will be developed to
include a gas station, a restaurant, a
fast food building, and a hotel
The developer has recently obtained a
building permit and nearly completed
the construction of the gas station
located near the intersection of 14
th
Street and Oak Glen Road. The
developer intends to hire a private
contractor to haul and dispose of the
sewage from the gas station and car
wash, so sewer service will not be
required initially. The developer
acknowledges that the gas station and
car wash will be connected to the
District’s sewer system when the lift
station is completed.
The District staff is working the developer to create a development agreement that would eliminate
the proposed lift station. The main points of the development agreement will be reviewed at the
board workshop.