Page 65 - Yucaipa Valley Water District - Board Workshop
P. 65
Workshop Memorandum No. 18-232 Page 2 of 5
Yucaipa Valley Water District - Actual AMI Meter Appurtenance Quantities
2018
Action Description Part
Q-1 Q-2 Q-3 Q-4
1" Fire Service Meters (Drinking Water) 1" FS iPearl 0 44 39 0
2018 Totals
New Homes 3/4" Irrigation Meter (Recycled Water) 3/4" iPearl 0 0 2 0
Radio Transceiver 520M Dual Port 0 44 115 0
Retro-Fit Radio Transceiver 520M Dual Port 0 745 185 0
3/4" Drinking Water Meter 3/4" iPearl 0 69 33 0
Replacement
Radio Transceiver 520M Dual Port 0 69 33 0
Other Larger Meter with Radio 520M Dual Port 0 2 2 0
1" Fire Service iPearl 0 44 39 0 83
3/4" iPearl 0 69 35 0 104
520M Dual Port Radio 0 860 333 0 1193
Totals
Other 0 2 2 0 4
Total Installations 0 862 409 0 1271
Installation Target 450 450 450 450 1800
Notes: The values assigned herein are the actual quantities installed.
Project Projections (Without Grant Funding): The task of installing 12,600 endpoints will take
approximately seven (7) years if the District staff installs 1,800 endpoints per year, 150 per month.
Updated Project Projections (With Grant Funding): The timeline of the project will be re-
evaluated with the additional funding from the WaterSMART grant. Once District staff meets with
the Bureau of Reclamation and further defines the applicable items for funding, District staff will
provide options and recommendations to expedite the project.
Yucaipa Valley Water District - October 9, 2018 - Page 65 of 172