Workshop Memorandum 18-247



                Date:              November 13, 2018

                Prepared By:       Matthew Porras, Implementation Manager

                Subject:           Status  Report  on  the  Construction  of  the  Replacement  of  Drinking  Water
                                   Pipelines on Douglas Street, Cornell Drive, Auburn Avenue, Citibank / Yucaipa
                                   Boulevard and Oak Glen Road


               On, June 5, 2018 the Board of Directors
               authorized District staff to solicit bids for
               the  construction  of  drinking  water
               pipelines  on  Douglas  Street,  Cornell
               Drive, Auburn Avenue, Citibank / Yucaipa
               Blvd  and  Oak  Glen  Road.    The  Project
               includes  the  construction  of  411  linear
               feet  of  6-inch  ductile  iron  pipe  in  the
               Citibank  /  Yucaipa  Blvd  area  and  3,409
               linear  feet  of  8-inch  ductile  iron  pipe  on
               Auburn  Avenue,  Cornell  Drive,  Douglas
               Street and Oak Glen Road.

               On July 25, 2018 the District received 4
               bids  for  the  Drinking  Water  pipeline
               replacement project as discussed at the
               regular Board Workshop on July 31, 2018
               [WM 18-192].

               On August 7, 2018, the Board of Directors awarded a construction contract to Borden Excavating
               [DM 18-114].  Borden Excavating started work on November 5, 2018 and is scheduled to be
               completed January 7,2018.  The current phasing will include the Citi-Bank segment first, the Oak
               Glen Road crossing second, and the residential subdivision third.

               The purpose of this item is informational, discussing the progress of the project.


               Financial Consideration

               The engineers estimate for this project was $1,100,000.  This project was included in the 2018-
               19 approved Capital Improvement Projects Budget.