Subject: Status Report on the Construction of the Replacement of Drinking Water
Pipelines on Douglas Street, Cornell Drive, Auburn Avenue, Citibank / Yucaipa
Boulevard and Oak Glen Road
On, June 5, 2018 the Board of Directors
authorized District staff to solicit bids for
the construction of drinking water
pipelines on Douglas Street, Cornell
Drive, Auburn Avenue, Citibank / Yucaipa
Blvd and Oak Glen Road. The Project
includes the construction of 411 linear
feet of 6-inch ductile iron pipe in the
Citibank / Yucaipa Blvd area and 3,409
linear feet of 8-inch ductile iron pipe on
Auburn Avenue, Cornell Drive, Douglas
Street and Oak Glen Road.
On July 25, 2018 the District received 4
bids for the Drinking Water pipeline
replacement project as discussed at the
regular Board Workshop on July 31, 2018
[WM 18-192].
On August 7, 2018, the Board of Directors awarded a construction contract to Borden Excavating
[DM 18-114]. Borden Excavating started work on November 5, 2018 and is scheduled to be
completed January 7,2018. The current phasing will include the Citi-Bank segment first, the Oak
Glen Road crossing second, and the residential subdivision third.
The purpose of this item is informational, discussing the progress of the project.
Financial Consideration
The engineers estimate for this project was $1,100,000. This project was included in the 2018-