Workshop Memorandum 19-003



                Date:              January 8, 2019

                Prepared By:       Matthew Porras, Implementation Manager

                Subject:           Status  Report  on  the  Construction  of  the  Replacement  of  Drinking  Water
                                   Pipelines on Douglas Street, Cornell Drive, Auburn Avenue, Citibank / Yucaipa
                                   Boulevard and Oak Glen Road


               Background

               On, June 5, 2018 the Board of
               Directors  authorized  District
               staff  to  solicit  bids  for  the
               construction    of   Drinking
               Water  Pipelines  on  Douglas
               Street, Cornell Drive, Auburn
               Avenue,  Citibank  /  Yucaipa
               Blvd  and  Oak  Glen  Road.
               The  project  includes  the
               construction of 411 linear feet
               of 6- inch ductile iron pipe in
               the  Citibank  /  Yucaipa  Blvd
               area and 3,409 linear feet of
               8-inch  ductile  iron  pipe  on
               Auburn     Avenue,    Cornell
               Drive,  Douglas  Street  and
               Oak Glen Road.

               On July 25, 2018 the District received 4 bids for the Drinking Water pipeline replacement project
               as discussed at the regular Board Workshop on July 31, 2018.

               On August 7, 2018, the Board of Directors awarded a construction contract to Borden Excavating.
               Borden Excavating started work on November 5, 2018 and is scheduled to be completed January
               7,2018.  The current phasing will include the Citi-Bank segment first, the Oak Glen Road crossing
               second, and the residential subdivision third.

               Current Update

               Borden has completed the installation of the water mainlines for the Citi-Bank and Oak Glen Road
               segments.    They  are  making  good  progress  in  the  residential  subdivision.    The  main  line
               installation  is  now  complete,  and  the  crews  are  working  on  the  installation  of  the  individual
               services with the road repair to follow.