Page 13 - Yucaipa Valley Water District
P. 13
C. Status Report on the Operational Status of the Wochholz Regional Water
Recycling Facility [Workshop Memorandum No. 19-074] - Operations Manager
Charles Thomas reported on the current status of the Wochholz Regional Water
Recycling Facility.
VI. Capital Improvement Projects
th
A. Status Report on the Construction of a 24-Inch Recycled Water Mainline in 7
Place, Calimesa [Workshop Memorandum No. 19-075] - Public Works Manager
th
John Wrobel reported on the status of the recycled water pipeline on 7 Place.
B. Status Report on the Construction of an 8-Inch Sewer Mainline in Yucaipa
Boulevard, Yucaipa [Workshop Memorandum No. 19-076] - Implementation
Manager Matthew Porras reported on the status of the sewer mainline construction
on Yucaipa Boulevard.
C. Status Report on the Geotechnical Investigation in the Vicinity of the Calimesa
Lake and Recharge Facility [Workshop Memorandum No. 19-077] -
Implementation Manager Matthew Porras reported on the status of the
geotechnical investigation at the Calimesa Lake and Recharge Facility.
VII. Public Policy
A. Discussion Regarding the Proposed Imported Water Rate Methodology for the San
Gorgonio Pass Water Agency [Workshop Memorandum No. 19-078] - General
Manager Joseph Zoba reported on the engineering workshop of the San Gorgonio
Pass Water Agency held on March 11, 2019.
VIII. Administrative Items
A. Presentation of the Unaudited Financial Report for the Period Ending on February
28, 2019 [Workshop Memorandum No. 19-079] - Chief Financial Officer Allison
Edmisten provided an overview of the unaudited financial report.
B. Automated Metering Infrastructure Project’s Compliance Completion Notification
from United States Bureau of Reclamation [Workshop Memorandum No. 19-080]
- Implementation Manager Katherine Hallberg reported on the status of the
District’s Automated Metering Infrastructure grant with the US Bureau of
Reclamation.
C. Rental of Bear Valley Mutual Water Company Stock Shares for the 2019 Irrigation
Season [Workshop Memorandum No. 19-081] - General Manager Joseph Zoba
reported on the anticipated rental of Bear Valley Mutual Water Company stock for
2019.
D. Consideration for ECORP Consulting to Extend the Original Study Area for the
Oak Valley Recharge Project for the Initial Study/ Mitigated Negative Declaration
[Workshop Memorandum No. 19-082] - Implementation Manager Katherine
Hallberg reported on the recommended additional scope of service for the
environmental investigation of the Calimesa Lake and Recharge Facility.
E. Discussion Regarding the Use of Political Consultants and Lobbyists for Calendar
Years 2019 and 2020 [Workshop Memorandum No. 19-083] - General Manager
Joseph Zoba reported on the status of contracts with the District’s lobbyist and
political consultant.
IX. Director Comments
X. Announcements - The future meetings were referenced on the workshop agenda.
XI. Closed Session - None
Yucaipa Valley Water District - Board Workshop Minutes Page 2 of 3
Yucaipa Valley Water District - March 19, 2019 - Page 13 of 71