Director Memorandum 19-064




                Date:              June 18, 2019

                                   Joseph Zoba, General Manager
                Prepared By:
                                   Allison Edmisten, Chief Financial Officer
                Subject:           Adoption of the Operating Budget and Capital Improvement Plan for Fiscal
                                   Year 2020

                Recommendation:        That the Board adopts the budget as presented.


               On Tuesday, June 11, 2019, the Yucaipa Valley Water District conducted a budget workshop to
               review the proposed operating budget for next year.  During the budget workshop, the District
               staff provided a detailed overview of each individual line item for the water, sewer, and recycled
               water enterprise funds of the District.

               There were no changes recommended to the budget other than minor language changes and
               clarification of various “miscellaneous” items.

                                                     Budget Overview

               The Fiscal  Year 2020 operating budget totals $27,974,659 (excluding capital improvement
               projects) distinguished by the following three enterprise funds.