Project Schedule
            Table 1 shows our proposed project schedule broken down by task. The Todd Groundwater Team can
            initiate the project upon receipt of a notice‐to‐proceed in August 2017 and anticipates that the project
            can be completed by November 2021. Based on our experience, this is a realistic schedule for completing
            the  scope  of  work  and  is  contingent  upon  the  timely  completion  of  the  USGS  model  and  strong
            cooperation of the YGSA and interested parties.
            As shown in the schedule, data collection and review (Task 1) and development of the hydrogeologic
            conceptual model (Task 2) is expected to take approximately one year with expected completion in July
            2019.  Development  of  sustainability  goal  and  management  criteria  (Task  3)  will  occur  over  the
            subsequent four‐month period (August through November 2019) followed by the identification and
            evaluation of future projects and management actions (Task 4) over a seven‐month period (December
            2019 through June 2010). Preparation of an implementation plan for the GSP (Task 5) is scheduled for
            completion by December 2020.

            It is anticipated that the administrative draft GSP would be prepared and submitted to the YGSA for
            review in April 2021. Comments received will be incorporated in the Draft GSP scheduled to be released
            to the public in June 2021. Comments received from the public will be incorporated into the Final GSP;
            the schedule allows for the subsequent required 90‐day review period. Final adoption is anticipated in
            October 2021 with submittal to DWR in November 2021. This schedule provides a buffer of two months
            before the DWR deadline.
            The thirteen TAC meetings identified in the GSP Work Plan are scheduled in relation to technical tasks
            to facilitate discussion of ideas and approaches for developing specific GSP sections and sharing of key
            findings and recommendations following the completion of technical analyses.
            Project Cost Estimate

            Table 2 shows the estimated “not‐to‐exceed” cost for the project by task. Hours are provided for all key
            team members, illustrating the emphasis on senior professionals for critical work tasks and use of more
            cost‐effective staff for technical support.




                                        Information redacted for evaluation purposes




















               Proposal – SBVMWD Groundwater                                           TODD GROUNDWATER
               Sustainability Plan for the Yucaipa Basin Area    13                                June 2018