P. 160

MONTHLY PROGRESS REPORT
                                     Yucaipa Basin Groundwater Sustainability Plan


                                                    NOVEMBER 2018

                                           Description of Work             Budget Used    Budget    % Complete   % Complete
           Task        Task Title                                  Budget
                                          Completed this Month             This Month   Remaining   by Budget   by Date
                                    Obtained USGS model files from
            1    USGS Groundwater Model Geoscience; began inspecting files   $       81,720  $       1,710  $      80,010   2.1%  5.0%
                                    and extracting information.
                                    Obtained info from Geoscience on
                 Current and Historical
            2                       YVWD well construction, water   $       49,440  $       2,160  $      47,280   4.4%  4.3%
                 Groundwater Conditions
                                    levels, water quality.
                 Plan Area Including Land  Draft figure of land use defined in
            3                                                    $       26,640  $       60  $      26,580   0.2%  11.0%
                 Use                2012 within basin boundary.

                                    Began preparing the draft annotated
           12.1  Prepare Admin Draft GSP                         $       53,120  $        120  $      53,000   0.2%  0.0%
                                    outline for the GSP.
                 Develop and Implement  Z. Carlson participated in kick-off
            15   Coordinated Outreach   meeting and reviewed preliminary  $       26,900  $        219  $      26,681   0.8%  8.1%
                 Plan               draft of

                                    S. Stuart & J. Weinberger prep for and
            17   GSA Meetings                                    $       29,760  $       3,120  $      26,640   10.5%  1.7%
                                    attend kick-off meeting.
                                    Correspondence with T. Kellett at
            19   Project Management  SBVMWD re project management;   $       96,000  $       3,480  $      92,520   3.6%  3.2%
                                    draft PM forms.

                 Total                                          $       814,500  $       10,869 $       803,631  1.3%


               The summary table above reflects services provided by Dudek from October 27 to November 30,
               2018, which includes costs billed to each task, a percent complete by budget and by date. Labor
               hours  billed  by  Dudek  staff  and  other  expenses,  if  charged,  for  this  billing  period  will  be
               presented in Dudek invoice #20187881 dated December 12, 2018.