P. 22










Workshop Memorandum 13-154



Date: September 10, 2013

Subject: Status Report on the Construction of the Casa Blanca / Highland
Avenue Water Mainline Replacement Project


At the regular meeting on August 21, 2013, the Board awarded a construction contract to TBU,
Inc. for the Casa Blanca / Highland Avenue Water Mainline Replacement Project [DM13-059].
This project consists of two 12-inch ductile iron pipe potable water lines in Casa Blanca Avenue
and Highland Avenue. One pipeline will replace approximately 1,700 feet of an existing 6-inch
high pressure steel distribution line. The second pipeline will replace approximately 1,650 feet
of an existing 12-inch low-pressure transmission line residing in an easement running through
several residential properties. Both new pipelines will be located in the public street right-of-way
of Casa Blanca and Highland Avenue. With the elimination of the existing easement line,
District liability will be reduced with easier long-term maintenance and repairs.

This project is categorically exempt from environmental review in accordance with the California
Environmental Quality Act Guidelines Section 15302(c).















































Yucaipa Valley Water District Board Workshop - September 10, 2013 - Page 22 of 84
   17   18   19   20   21   22   23   24   25   26   27