Director Memorandum 17-007




                Date:              January 3, 2017

                Prepared By:       Brent Anton, Engineering Manager

                Subject:           Notice of Completion for the Contract with Weka, Inc. for the Construction of
                                   the RWB-12.4 Interim Booster Station


                Recommendation:        That the Board authorizes the filing of the Notice of Completion and
                                       release of the retention amount of $15,888.70 thirty-five days after the
                                       recorded date.

               On August 5, 2015, the Board of Directors authorized the District  staff to solicit bids for the
               construction of an interim recycled water booster station at the intersection of Myrtlewood Drive
               and California Street.  The project included the construction of a 300 gallon per  minute pre-
               packaged booster station, approximately 200 linear feet of 24”, 20” and 12” piping and electrical
               work [Director Memorandum 15-074]..

































               On October 7, 2015, the Board of Directors approved a contract with Weka, Inc. to construct the
               facility for a sum not to exceed $317,772 [Director Memorandum No. 15-091].

               The project is now complete and based on  the letter from Krieger & Stewart; District staff
               recommends that the Board authorizes the filing of the Notice of Completion and release of the
               retention amount of $15,888.70 thirty-five days after the recorded date.