Workshop Memorandum 17-070
Date: May 30, 2017
From: Matthew Porras, Management Analyst
Subject: Status Report on the Construction of Replacement Pipelines on Date Avenue,
Dodd Street, Panorama Drive, Lennox Street, Verona Street, Calvin Street, and
Vista Lane - Yucaipa
On April 4, 2017, the Board of Directors awarded a construction project to Borden Excavating for
the construction of replacement pipelines on Date Avenue, Dodd Street, Panorama Drive, Lennox
Street, Verona Street, Calvin Street, and Vista Lane Replacement Pipelines [Director
Memorandum No. 17-032]. The project includes the construction of approximately 4,600+ linear
feet of 8-inch mortar lined ductile iron pipe, including various laterals, valves and appurtenances,
and removal and replacement of pavement.
The purpose of this agenda item is to provide an update on the current construction activities.