Workshop Memorandum 17-080



                Date:          June 13, 2017

                From:          Kathryn Hallberg, Management Analyst

                Subject:       Status  Report  on  the  Construction  of  the  Site  Improvements  for  the  Recycled
                               Water Booster Station 12.4.0 in Calimesa

               On  January  31,  2017, the  Board  of  Directors  awarded  the  contract  to TSR  Construction  and
               Inspection for the construction of the site improvements at RWB- 12.4 Recycled Booster Station
               at the intersection of Myrtlewood Drive and California Street in Calimesa

               The project includes the construction of 315± linear feet of 8-foot 8-inch to 12-foot high masonry
               walls with masonry pillars, 200± linear feet of 8-foot high steel tubular fencing with access gates,
               site grading and furnishing, Class 2 base material, and site landscaping.