Workshop Memorandum 17-081



                Date:          June 13, 2017

                From:          Matthew Porras, Management Analyst

                Subject:       Status  Report  on  the  Construction  of  Replacement  Pipelines  on  Date  Avenue,
                               Dodd Street, Panorama Drive, Lennox Street, Verona Street, Calvin Street, and
                               Vista Lane - Yucaipa


               On April 4, 2017, the Board of Directors awarded a construction project to Borden Excavating for
               the construction of replacement pipelines on Date Avenue, Dodd Street, Panorama Drive, Lennox
               Street,  Verona  Street,  Calvin  Street,  and  Vista  Lane  Replacement  Pipelines  [Director
               Memorandum No.  17-032].  The project includes the construction of approximately 4,600+ linear
               feet of 8-inch mortar lined ductile iron pipe, including various laterals, valves and appurtenances,
               and removal and replacement of pavement.











































               The purpose of this agenda item is to provide an update on the current construction activities.