Workshop Memorandum 18-008
Date: January 9, 2018
From: Kathryn Hallberg, Management Analyst
Matt Porras, Management Analyst
Subject: Status Report on the Construction of an 8-Inch Sewer Mainline in Yucaipa
Boulevard
The City of Yucaipa is preparing to proceed with the Yucaipa Boulevard Widening Project that
involves the widening and reconstruction of Yucaipa Boulevard from 18 Street to Avenue
th
E/Hampton Road. In conjunction with this project, the District is preparing to proceed with sewer
construction consisting of approximately 2,400 linear feet of 8-inch main line in Yucaipa Boulevard
th
between 18 Street and Avenue E/Hampton Road as well as Ridgecrest Drive between Yucaipa
Boulevard and Sierra Linda Street.
The sewer main project is categorically exempt from environmental review in accordance with
the California Environmental Quality Act Guidelines Section 15301(C).