Workshop Memorandum 18-060



                Date:          February 13, 2018

                From:          Matt Porras, Management Analyst

                Subject:       Status  Report  on  the  Construction  of  an  8-Inch  Sewer  Mainline  in  Yucaipa
                               Boulevard

               The City of Yucaipa is preparing to proceed with the Yucaipa Boulevard Widening Project that
                                                                                         th
               involves  the  widening  and  reconstruction  of  Yucaipa  Boulevard  from  18   Street  to  Avenue
               E/Hampton Road.  In conjunction with this project, the District is preparing to proceed with sewer
               construction consisting of approximately 2,400 linear feet of 8-inch main line in Yucaipa Boulevard
               between 18  Street and Avenue E/Hampton Road as well as Ridgecrest Drive between Yucaipa
                           th
               Boulevard and Sierra Linda Street.









































               The sewer main project is categorically exempt from environmental review in accordance with
               the California Environmental Quality Act Guidelines Section 15301(C).