Page 13 - Yucaipa Valley Water District - Board Workshop
P. 13
Workshop Memorandum 18-256
Date: November 27, 2018
Prepared By: Matthew Porras, Implementation Manager
Subject: Status Report on the Construction of the Replacement of Drinking Water
Pipelines on Douglas Street, Cornell Drive, Auburn Avenue, Citibank / Yucaipa
Boulevard and Oak Glen Road
On, June 5, 2018 the
Board of Directors
authorized District
staff to solicit bids for
the construction of
Drinking Water
Pipelines on Douglas
Street, Cornell Drive,
Auburn Avenue,
Citibank / Yucaipa
Blvd and Oak Glen
Road. The project
includes the
construction of 411
linear feet of 6- inch
ductile iron pipe in
the Citibank /
Yucaipa Blvd area
and 3,409 linear feet
of 8-inch ductile iron
pipe on Auburn
Avenue, Cornell
Drive, Douglas
Street and Oak Glen
Road.
On July 25, 2018 the District received 4 bids for the Drinking Water pipeline replacement project
as discussed at the regular Board Workshop on July 31, 2018.
On August 7, 2018, the Board of Directors awarded a construction contract to Borden Excavating.
Borden Excavating started work on November 5, 2018 and is scheduled to be completed January
7,2018. The current phasing will include the Citi-Bank segment first, the Oak Glen Road crossing
second, and the residential subdivision third.
The purpose of this item is informational, discussing the progress of the project.
Yucaipa Valley Water District - November 27, 2018 - Page 13 of 37