Workshop Memorandum 18-255
Date: November 27, 2018
Prepared By: Matthew Porras, Implementation Manager
Subject: Status Report on the Construction of an 8-Inch Sewer Mainline in Yucaipa
Boulevard
On October 4, 2016, the Board of Directors
authorized the General Manager to execute
an Agreement between The City of Yucaipa
and The Yucaipa Valley Water District for
Yucaipa Boulevard Sewer Utility [Director
Memorandum No. 16-094].
On November 14, 2017, the Board of
Directors authorized the District staff to solicit
bids for the construction of Yucaipa Boulevard
Sewer from Hampton Road to 18th Street
[Workshop Memorandum No. 17-163]. The
project includes the construction of
approximately 2,550 linear feet of 8-inch
Vitrified Clay Pipe, including manholes,
laterals and appurtenances. The sewer main
project is categorically exempt from
environmental review in accordance with the
California Environmental Quality Act Guidelines Section 15301(C).
As discussed in a Board Workshop on February 13, 2018, the District received 6 bids for the
pipeline project. Weka, Inc. was the low bidder in the amount of $526,193.00. On February 20,
2018 at a regular Board Meeting [Director Memorandum 18-035] the Board of Directors awarded
a construction contract with Weka, Inc. to complete the project. The contractor is scheduled to
start work in the month of November 2018 and is scheduled to complete within 60 working days
on the project.
The sewer main project is categorically exempt from environmental review in accordance with the
California Environmental Quality Act Guidelines Section 15301(C).
Financial Consideration
Funding for this project will be from Sewer Fund, Infrastructure Reserves [GL Account #03-
10311]. This project was not included in the 2017-18 budget, however, there is sufficient funding
available in the reserve fund listed above.
Yucaipa Valley Water District - November 27, 2018 - Page 10 of 37