Page 23 - Yucaipa Valley Water District - Board Workshop
P. 23

Workshop Memorandum 18-265



                Date:              December 11, 2018

                Prepared By:       Matthew Porras, Implementation Manager

                Subject:           Status  Report  on  the  Construction  of  the  Replacement  of  Drinking  Water
                                   Pipelines on Douglas Street, Cornell Drive, Auburn Avenue, Citibank / Yucaipa
                                   Boulevard and Oak Glen Road


               Project Overview: On,
               June 5, 2018 the Board
               of  Directors  authorized
               District  staff  to  solicit
               bids for the construction
               of    Drinking    Water
               Pipelines  on  Douglas
               Street,  Cornell  Drive,
               Auburn         Avenue,
               Citibank / Yucaipa Blvd
               and  Oak  Glen  Road.
               The project includes the
               construction   of   411
               linear  feet  of  6-  inch
               ductile  iron  pipe  in  the
               Citibank / Yucaipa Blvd
               area  and  3,409  linear
               feet  of  8-inch  ductile
               iron  pipe  on  Auburn
               Avenue,  Cornell  Drive,
               Douglas Street and Oak
               Glen Road.

               On July 25, 2018 the District received 4 bids for the Drinking Water pipeline replacement project
               as discussed at the regular Board Workshop on July 31, 2018.

               On August 7, 2018, the Board of Directors awarded a construction contract to Borden Excavating.
               Borden Excavating started work on November 5, 2018 and is scheduled to be completed January
               7,2018.  The current phasing will include the Citi-Bank segment first, the Oak Glen Road crossing
               second, and the residential subdivision third.

               Current Update: Borden has completed the installation of the mainlines for the Citi-Bank and
               Oak Glen Road segments.  They are making good progress in the residential subdivision.  After
               the mainline is complete, new residential services will be installed with the road repair to follow.








                                      Yucaipa Valley Water District - December 11, 2018 - Page 22 of 111
   18   19   20   21   22   23   24   25   26   27   28