Director Memorandum 19-008




                 Date:             January 15, 2019

                 Prepared By:      Matthew Porras, Implementation Manager

                 Subject:          Consideration  of  Purchasing  Temporary  Pipe  Materials  for  the  Calimesa
                                   Lakes Recharge Study


                 Recommendation:       That the Board Authorize the General Manager to Execute a Contract
                                       for  Purchase  of  Temporary  Pipe  Materials  for  the  Calimesa  Lakes
                                       Recharge Study.

               As  a  part  of  the  Calimesa  Lakes  project,
               the District has contracted with Geoscience
               who will be conducting recharge testing by
               discharging water into constructed basins
               with the point of discharge depicted in this
               conceptual  drawing.    The  testing  is
               scheduled to last 6-8 weeks.  The lead time
               on  the  pipe  and fittings is  estimated  at  3
               weeks.

               The water supply source for the recharge
               testing will be from a fire hydrant within the
               Summerwind  Trails  development.    The
               pipeline path is estimated to be just under
               1,000 linear feet.

               As a part of the Geoscience contract, the District is responsible to furnish and install the temporary
               supply piping.  The temporary piping can be either rented or purchased.  Based on discussions
               at during the Board Workshop held on January 8, 2019 [Workshop Memorandum 19-013], District
               staff recommends purchasing the pipe and fittings for this project due to the future cost savings
               when  compared  to  a  second  rental.   The  costs  associated  with  the  rental  option  include  the
               consideration of the rental cycle of 28 days and the estimated timeframe of the project of 6-8
               weeks totaling at least two rental cycles.  If the project exceeds the estimated timeframe, the
               rental cost will quickly exceed the purchase cost.  Additionally, having this pipe and fittings on
               hand will improve the District’s response time for emergency response and future use of this pipe
               material.