Workshop Memorandum No. 19-090                                                     Page 18 of 19



                                          YUCAIPA VALLEY WATER DISTRICT
                                          CAPITAL IMPROVEMENT PROGRAM

                 Project     Public Works – Wildwood Creek Sewer Replacement and Realignment



                 Division    Wastewater                               Project Priority        Important


                                                                      Projected Start
                Category     Rehabilitation and Realignment                                     2019-7
                                                                           Date

                  Phase          Planning             Design           Environmental         Construction


                  Notes



                                  COST BY TYPE                                   FUNDING SOURCE
                Preliminiary Engineering/Design                $ 0   Reserves/Depreciation          $ 475,000
                Environmental                                  $ 0   Development Impact Fees              $ 0
                Right-of-Way/Land Acquisition                  $ 0   Federal Participation                $ 0
                Labor, Equipment, Administration               $ 0   State Participation                  $ 0
                Contract Construction                     $ 475,000  Bond Financing                       $ 0
                Construction Engineering                       $ 0   Local Matching                       $ 0
                Other: Environmental/Permitting/Misc           $ 0   Other Funds                          $ 0
                                             Total        $ 475,000                    Total        $ 475,000


               Project Description:

               The Wildwood Creek Sewer pipeline was damaged during a storm on February 16, 2019. The
               sewer mainline will be realigned in to Wildwood Canyon Road.






























                                       Yucaipa Valley Water District - March 26, 2019 - Page 49 of 202