Workshop Memorandum No. 19-090 Page 18 of 19
YUCAIPA VALLEY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Project Public Works – Wildwood Creek Sewer Replacement and Realignment
Division Wastewater Project Priority Important
Projected Start
Category Rehabilitation and Realignment 2019-7
Date
Phase Planning Design Environmental Construction
Notes
COST BY TYPE FUNDING SOURCE
Preliminiary Engineering/Design $ 0 Reserves/Depreciation $ 475,000
Environmental $ 0 Development Impact Fees $ 0
Right-of-Way/Land Acquisition $ 0 Federal Participation $ 0
Labor, Equipment, Administration $ 0 State Participation $ 0
Contract Construction $ 475,000 Bond Financing $ 0
Construction Engineering $ 0 Local Matching $ 0
Other: Environmental/Permitting/Misc $ 0 Other Funds $ 0
Total $ 475,000 Total $ 475,000
Project Description:
The Wildwood Creek Sewer pipeline was damaged during a storm on February 16, 2019. The
sewer mainline will be realigned in to Wildwood Canyon Road.
Yucaipa Valley Water District - March 26, 2019 - Page 49 of 202