Workshop Memorandum No. 19-090 Page 15 of 19
YUCAIPA VALLEY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Project YVRWFF – Perimeter Fencing Upgrade for Intrusion Protection
Division Water Project Priority Important
Projected Start
Category Facility Improvement 2019-6
Date
Phase Planning Design Environmental Construction
Notes
COST BY TYPE FUNDING SOURCE
Preliminiary Engineering/Design $ 0 Reserves/Depreciation $ 0
Environmental $ 0 Development Impact Fees $ 100,000
Right-of-Way/Land Acquisition $ 0 Federal Participation $ 0
Labor, Equipment, Administration $ 100,000 State Participation $ 0
Contract Construction $ 0 Bond Financing $ 0
Construction Engineering $ 0 Local Matching $ 0
Other: Environmental/Permitting/Misc $ 0 Other Funds $ 0
Total $ 100,000 Total $ 100,000
Project Description:
The property line that is in conjunction with the Stater Bros. property directly adjacent to the
YVRWFF has had multiple intrusions from the low block wall that belongs to Stater Bros. We’ve
reached out to Stater Bros. to allow us to heighten the block wall to 8 ft. Depending on the grade
the addition of 2 to 4 ft. of block will need to be added.
Yucaipa Valley Water District - March 26, 2019 - Page 46 of 202