Page 41 - Yucaipa Valley Water District - Board Workshop
P. 41
Workshop Memorandum No. 19-090 Page 10 of 19
YUCAIPA VALLEY WATER DISTRICT
CAPITAL IMPROVEMENT PROGRAM
Project WRWRF – Primary Flights Refurbishing and Replacements
Division Wastewater Project Priority Important
Projected Start
Category Asset Rehabilitation 2019-2
Date
Phase Planning Design Environmental Construction
Notes
COST BY TYPE FUNDING SOURCE
Preliminiary Engineering/Design $ 0 Reserves/Depreciation $ 150,000
Environmental $ 0 Development Impact Fees $ 0
Right-of-Way/Land Acquisition $ 0 Federal Participation $ 0
Labor, Equipment, Administration $ 150,000 State Participation $ 0
Contract Construction $ 0 Bond Financing $ 0
Construction Engineering $ 0 Local Matching $ 0
Other: Environmental/Permitting/Misc $ 0 Other Funds $ 0
Total $ 150,000 Total $ 150,000
Project Description:
Concrete refinishing and coating replacement of primary effluent launder. Primary metal launder
needs to be replaced by fiberglass launder. Launders need concrete coating replacement and
door and hinge refurbishing. Metal doors need to be refurbished and hinges replaced due to rot.
Yucaipa Valley Water District - March 26, 2019 - Page 41 of 202