Fox Canyon Groundwater Sustainability Plans
            Client:           FCGMA
            Dates:            2016–Present
            Key Dudek Staff:  Peter Quinlan, Ron Schnabel (Project Manager), Jill Weinberger, Daniel Ritter, Hugh
                              McManus, Dylan Duvergé, Jane Gray, Zoe Carlson, Becky Golden-Harrell
            Reference:        Jeff Pratt, Director of Watershed Protection District, 805.645.2014,
                              Jeff.Pratt@ventura.org

            The FCGMA retained Dudek in
            2016 to prepare the GSPs for the
            Oxnard, Las Posas, and Pleasant
            Valley basins in Ventura County.
            These basins were designated
            high priority by DWR for overdraft
            and water quality. The plan
            requirements include historical
            basin and water use conditions,
            including an annual water budget
            for the 30-year period from 1985–
            2015; determination of
            sustainable basin yield and
            associated uncertainty; definition
            of undesirable results and
            minimum thresholds; and identification of water resource projects or management actions
            necessary to achieve sustainable management by 2040. After compiling and evaluating existing
            data from multiple agencies, Dudek completed preliminary drafts of the GSPs in November 2017,
            which were released for public review. Dudek has led stakeholder outreach efforts throughout the
            development of the GSPs including development of an outreach and engagement plan, ongoing
            communication with more than 400 interested parties through electronic newsletters, facilitating
            six stakeholder meetings and leading two workshops for the FCGMA Board of Directors. We are
            proceeding with incorporating the feedback received from stakeholders during the review process
            and revising the initial conditions for the numerical model simulations of future conditions. The
            plans are scheduled for completion by the fall of 2018.