• Water Systems Consulting - 9:00 am
The following representatives from Water Systems Consulting provided a
presentation to the Board of Directors:
Michael Cruikshank, Project Manager
Jeffery Szytel, Principal in Charge
Laine Carlson, Management Actions, Project Development
Brian Villalobos, Geohydrology
Johnson Yeh, Groundwater Modeling
This team also answered questions from the Board of Directors of the
Yucaipa Sustainable Groundwater Management Agency.
• Dudek - 10:00 am
The following representatives from Dudek provided a presentation to the
Board of Directors:
Peter Quinlan, Principal in Charge
Steven Stuart, Project Manager
Jill Weinberger
Kyle Harper
Zoe Carlson
This team also answered questions from the Board of Directors of the
Yucaipa Sustainable Groundwater Management Agency.
• Todd Groundwater - 11:00 am
The following representatives from Todd Groundwater provided a
presentation to the Board of Directors:
Edwin Lin, Project Manager
Phyllis Stanin, Technical Oversight
Mark Sillings, Public Outreach
Esmerelda Garcia, Public Outreach
Ben Willardson, Project Engineering Design and Costing
This team provided a presentation and answered questions from the
Board of Directors of the Yucaipa Sustainable Groundwater Management
Agency.
Following a lengthy discussion by the Board of Directors of the Yucaipa
Sustainable Groundwater Management Agency, Joseph Zoba moved to have
Joseph Zoba, Mark Iverson, and David Armstrong meet with representatives from
Dudek to negotiate a revised scope of services and project cost. Ray Casey
seconded the motion. The motion was approved by a unanimous vote of the board
members.