Page 10 - Yucaipa Sustainable Groundwater Management Agency - Yucaipa SGMA
P. 10
November Nov 5‐11
Oct 29‐Nov 4
Oct 22‐28
Oct 15‐21
October
Oct 8‐14
Oct 1‐7
Sep 24‐30
Sep 17‐23
September Sep 10‐16
Sep 3‐9
Aug 27‐Sep2 Yucaipa Sustainable Groundwater Management Agency - August 29, 2018 - Page 9 of 25
Aug 20‐26
August Aug 13‐19
Aug 6‐12
Jul 30‐Aug 5 = Infiltration Testing End (Site Demobilization and Restoration/Equipment Transfer to Next Site [if applicable])
July 23‐29 = Site Preparation (Excavation/Fencing/Equipping/Start Fill) = Infiltration Testing (Process Monitoring/Data Collection)
July
Jul 16‐22
July 9‐15
Completed
Table 1. Project Schedule (revised 2018‐08‐14)
Dates (Mon ‐ Sun) Skid A A.7A South of Yucaipa Creek at California St. (EX‐5) A.9A Oak Glen Creek Basins (EX‐2) ‐ Bermed A.9A Oak Glen Creek Basins (EX‐2) ‐ Excavated Skid B A.5 Oak Glen Creek ‐ Western Heights (EX‐9)
Month
Task 2. Infiltration Testing A.1 Tennessee Street Basins A.3 Chapman Heights Basin A.7 Yucaipa Creek at California St. (EX‐5) B.2 Dunlap Channel B.4 10th St. and Avenue E (EX‐7) B.8 Wilson Creek Basins (EX‐1) B.6 Wilson Creek III (EX‐3) B.10 Wildwood Creek Basins (EX‐4) Task 3. Draft and Final Reports 3.1. Prepare Draft Report Agency Review 3.2. Prepare Final Report