              VII.     Reports

                       A.     Report from Engineering Consultant – Tom Harder, ALDA Engineering

                              Mr. Harder requested that any comments on the draft Beaumont Basin
                              Storage Loss Analysis to be submitted soon.

                       B.     Report from Legal Counsel – Thierry Montoya, Alvarado Smith

                              Legal Counsel Thierry Montoya  drew attention to the May 15, 2018
                              water right transfer memorandum in follow up to a request at the prior
                              meeting regarding transfer of overlying rights to appropriative rights via
                              sale or other transfer permitted by the judgment.

             VIII.     Discussion Items

                       A.     Status  Report  on  Beaumont  Basin  Water  Level  Monitoring  Program
                              through May 29, 2018

                                     Recommendation:  No recommendation.

                                     Engineer Hannibal Blandon advised that a new temporary probe
                                     has been installed at Well 29. At Oak Valley #5 a communications
                                     cable is not working, but water levels have been stable within 6
                                     feet. The Noble Creek observation wells have seen a significant
                                     rise over the last year and a half. On the south side, the Summit
                                     Cemetery varies due to pumping at a nearby well. The Sun lakes
                                     well is fairly flat. On the east, Banning well 8 had lost the probe.
                                     It will be pulled and a new probe will be installed this summer.
                                     Well 15 has a flat levels, but Well 9 shows some fluctuating due
                                     to nearby pumping. Two wells centrally located show significant
                                     variation due to pumping. Potential for additional monitoring wells
                                     is being pursued on a property owned by the Catholic Diocese,
                                     and at YVWD Lift Station #2.


                       B.     Consideration of the Watermaster Budget for Fiscal Year 2018-19
                                     Recommendation:  That the Watermaster Committee approve the
                                     budget for Fiscal Year 2018-019 and authorize the preparation of
                                     an  Independent  Accountant’s  Financial  Report  for  Fiscal  Year
                                     2017-18.





               4667987.1 -- N1356.1