Page 38 - Yucaipa Valley Water District - Board Workshop
P. 38

Workshop Memorandum 19-028



                Date:              January 29, 2019

                Prepared By:       Matthew Porras, Implementation Manager

                Subject:           Status Report on the Construction of an 8-Inch Sewer Mainline in Yucaipa
                                   Boulevard

               Project Overview: On October 4, 2016, the
               Board  of  Directors  authorized  the  General
               Manager to execute an Agreement between
               The City of Yucaipa and The Yucaipa Valley
               Water  District for  Yucaipa  Boulevard  Sewer
               Utility [Director Memorandum No. 16-094].

               On  November  14,  2017,  the  Board  of
               Directors authorized the District staff to solicit
               bids for the construction of Yucaipa Boulevard
               Sewer  from  Hampton  Road  to  18th  Street
               [Workshop  Memorandum  No.  17-163].  The
               project   includes   the    construction   of
               approximately  2,550  linear  feet  of  8-inch
               Vitrified  Clay  Pipe,  including  manholes,
               laterals and appurtenances.  The sewer main
               project   is   categorically   exempt   from
               environmental review in accordance with the
               California Environmental Quality Act Guidelines Section 15301(C).

               As discussed in a Board Workshop on February 13, 2018, the District received 6 bids for the
               pipeline project. Weka, Inc. was the low bidder in the amount of $526,193.00.  On February 20,
               2018 at a regular Board Meeting [Director Memorandum 18-035] the Board of Directors awarded
               a construction contract with Weka, Inc. to complete the project.

               Financial  Consideration:  Funding  for  this  project  will  be  from  Sewer  Fund,  Infrastructure
               Reserves  [GL  Account  #03-10311].    This  project  was  not  included  in  the  2017-18  budget,
               however, there is sufficient funding available in the reserve fund listed above.

               Current Update: The District’s contractor (Weka, Inc.) is constructing lateral lines in the areas of
               completed main line.  Although the District’s contractor experienced numerous conflicts in the
               main line installation, as well as a few rain days, the project’s overall timeline remains mostly
               intact.  City of Yucaipa is providing traffic control in Yucaipa Boulevard for the District’s contractor.











                                       Yucaipa Valley Water District - January 29, 2019 - Page 37 of 100