Workshop Memorandum 19-027
Date: January 29, 2019
Prepared By: Matthew Porras, Implementation Manager
Subject: Status Report on the Construction of the Replacement of Drinking Water
Pipelines on Douglas Street, Cornell Drive, Auburn Avenue, Citibank / Yucaipa
Boulevard and Oak Glen Road
Project Overview: On,
June 5, 2018 the Board
of Directors authorized
District staff to solicit
bids for the construction
of Drinking Water
Pipelines on Douglas
Street, Cornell Drive,
Auburn Avenue,
Citibank / Yucaipa Blvd
and Oak Glen Road.
The project includes the
construction of 411
linear feet of 6- inch
ductile iron pipe in the
Citibank / Yucaipa Blvd
area and 3,409 linear
feet of 8-inch ductile
iron pipe on Auburn
Avenue, Cornell Drive,
Douglas Street and Oak
Glen Road.
On July 25, 2018 the District received 4 bids for the Drinking Water pipeline replacement project
as discussed at the regular Board Workshop on July 31, 2018.
On August 7, 2018, the Board of Directors awarded a construction contract to Borden Excavating.
Borden Excavating started work on November 5, 2018 and is scheduled to be completed January
7,2018. The current phasing will include the Citi-Bank segment first, the Oak Glen Road crossing
second, and the residential subdivision third.
Current Update: Borden has completed the installation of the mainlines for the Citi-Bank and
Oak Glen Road segments. They are making good progress in the residential subdivision. The
main line installation is now complete, and the crews are working on the installation of the
individual services with the road repair to follow.