Workshop Memorandum No. 19-094                                                       Page 2 of 4


               To fully remediate and recover from
               the storm damage, the District staff
               is  proposing  to  relocate  the  sewer
               mainline  to  the  north  in  Wildwood
               Canyon  Road.    This  proposed
               project  would  approximately  1,300
               lineal  feet  of  a  new  10”  diameter
               segment  of  sewer  mainline  in
               Wildwood  Canyon  Road  to  convey
               the sewer flows from the upstream
               development.
               In addition to the upstream flow that
               will  be  diverted  with  this  new
               alignment,    future    connections
               downstream  of  the  damaged  pipe
               that  remain  in  the  creek  area  are
               also being reviewed and may need
               to  be  fortified  or  realigned  for
               increased  protection  from  future
               storm flow damage.

               In the adjacent figure, this project is
               labeled  “New  Alignment  No.1”  and
               the  next  phased  improvement  as
               “New Alignment No.2”.  The second
               phased       improvement      (New
               Alignment No.2) is recommended to
               secure  a  segment  of  sewer  main
               approximately  700  linear  feet  long
               that  will  likely  be  damaged  during
               future  storm  events.    The  New
               Alignment No.2 can be constructed
               at  a  later  date  after  the  New
               Alignment  No.1  is  complete.    The
               result of these two new alignments
               would allow an approximately 2,800
               linear foot segment sewer mainline
               to be removed from service.

               To expedite this project, District staff
               will  acquire  bids  and  bring  them
               back  for  Board  consideration  as
               soon as the design is complete.  The
               project completion goal is June 30,
               2019.