Page 9 - Yucaipa Valley Water District - Board Workshop
P. 9

Workshop Memorandum 19-093



                Date:              April 9, 2019

                Prepared By:       Matthew Porras, Implementation Manager

                Subject:           Overview  of  the  Anticipated  Notice  of  Completion  for  the  8-Inch  Sewer
                                   Mainline Project in Yucaipa Boulevard, Yucaipa

               On October 4, 2016, the Board of Directors
               authorized the General Manager to execute
               an  Agreement  between  the  City  of  Yucaipa
               and  the  Yucaipa  Valley  Water  District  for
               Yucaipa  Boulevard  Sewer  Utility  [Director
               Memorandum No. 16-094].

               On  November  14,  2017,  the  Board  of
               Directors authorized the District staff to solicit
               bids for the construction of Yucaipa Boulevard
               Sewer  from  Hampton  Road  to  18th  Street
               [Workshop Memorandum No. 17-163].  The
               project   includes   the    construction   of
               approximately  2,550  linear  feet  of  8-inch
               vitrified  clay  pipe,  including  manholes,
               laterals, and appurtenances.  The sewer main
               project   is   categorically   exempt   from
               environmental review in accordance with the
               California Environmental Quality Act Guidelines Section 15301(C).

               The District’s contractor (Weka, Inc.) has completed the installation of the sewer mainline, laterals
               and appurtenances in Yucaipa Boulevard and Ridgecrest Drive.  The sewer is now available for
               connections from customers.

               The  project  is  now  complete  and  based  on  the  letter  from  Krieger  &  Stewart;  District  staff
               recommends that the Board authorize the filing of the attached Notice of Completion and the
               payment.