Page 5 - Yucaipa Valley Water District - Board Workshop
P. 5

Workshop Memorandum 19-104



                Date:          April 30, 2019

                From:          Kathryn Hallberg, Implementation Manager

                Subject:       Status Report on the Installation of the Advanced Metering Infrastructure System


               Yucaipa  Valley  Water  District  was  awarded  a  $1,000,000  WaterSMART:  Water  and  Energy
               Efficiency Grant on October 2, 2018 for the District’s Advanced Metering Infrastructure (AMI)
               Project.  On March 7, 2019, the District was notified the environmental compliance activities are
               complete and the construction for the project may begin.  The projected AMI project schedule is
               depicted below.  On April 10, 2019 the District participated in a call with the United States Bureau
               of Reclamation to discuss the next steps, which required additional documentation which has
               been completed and submitted.


                                AMI Project - Projected/Estimated Meter Appurtenance Quantities
                                                              Quarterly Install Rate       2019 Estimates
                        Action           Description
                                                            Q-1    Q-2    Q-3     Q-4   Quantity     Cost
                       Retro-Fit      Radio Transceiver   1,200  1,200  1,200  1,200       4,800    $771,000
                     Replacement      AMI Capable Meter
                                          and Radio          50     50     50     50         200     $58,000
                                         Transceiver
                     Replacement        Smart Point Lid    1,250  1,250  1,250  1,250      5,000    $162,000
                           Endpoint Installations          1,250  1,250  1,250  1,250      5,000    $991,000
                                                              Quarterly Install Rate       2020 Estimates
                        Action           Description
                                                            Q-1    Q-2    Q-3     Q-4   Quantity     Cost
                       Retro-Fit      Radio Transceiver      54     54     54     54         216     $34,700
                     Replacement      AMI Capable Meter
                                          and Radio         912    912    912     912      3,648  $1,052,000
                                         Transceiver
                     Replacement        Smart Point Lid     966    966    966     966      3,864     $32,000
                           Endpoint Installations            966    966    966    966      3,864  $1,118,700
                                                              Quarterly Install Rate       2021 Estimates
                        Action           Description
                                                            Q-1    Q-2    Q-3     Q-4   Quantity     Cost
                       Retro-Fit      Radio Transceiver      0      0       0      0           0          $0
                     Replacement      AMI Capable Meter
                                          and Radio         912    912    912     912      3,648  $1,052,000
                                         Transceiver
                     Replacement        Smart Point Lid     912    912    912     912      3,648     $30,000
                           Endpoint Installations            912    912    912    912      3,648  $1,082,000
                                                           Total Installations 2019-2021    12,512  $3,191,700






                                         Yucaipa Valley Water District - April 30, 2019 - Page 5 of 114