Director Memorandum No. 19-067                                                       Page 3 of 8


               Traffic Control Coordination

               District staff has coordinated with the City of Yucaipa regarding the option to detour the vehicular
               traffic  on  Wildwood  Canyon  Road  during  the  construction  work  hours  to  provide  a  safe  and
               efficient alternative to allowing traffic to enter the work area in the vicinity of a trench that will vary
               from 14-17 feet deep.






































               Financial Considerations

               District staff attended the 2019 February Storm Event Applicants Briefing on June 5, 2019 and
               filed an initial application for the resulting storm damage of the incident  (CDAA 2019-02) with
               California Governor’s Office of Emergency Services.  This funding reimbursement opportunity
               may cover up to 75% of the project costs.  Depending on the result of the State funding, the
               remaining balance will be funded from Sewer Fund, Infrastructure Reserves [GL Account #03-
               10311] as there is sufficient funding available.