                                                          EXHIBIT I

                                    MONITORING AND MAINTENANCE PLAN COMPONENTS


        For Category 1 Implementation Projects Only

        Introduction
          Goals and objectives of project
          Site location and history

          Improvements implemented
        Monitoring and Maintenance Plan

          Monitoring Metrics (ex: Plant establishment, bank erosion, hydraulic characteristics, habitat expansion)
          Maintenance Metrics (ex: irrigation, pest management, weed abatement, continuous invasive species
            removal until natives established)
          Special Environmental Considerations (ex: resource agency requirements, permit requirements,
            CEQA/NEPA mitigation measures)
          Performance Measures, or success/failure criteria monitoring results measured against (ex: percent
            canopy cover after 1, 5, 10 years, water temperature decrease, site specific sediment scour or retention)
          Method of Reporting (ex: paper reports, online databases, public meetings)
          Frequency of Duration Monitoring and Reporting (daily, weekly, monthly, yearly)

          Frequency and Duration of Maintenance Activities
          Responsible Party (who is conducting monitoring and/or maintenance) Implementing responsibility (i.e.,
            who is responsible for monitoring and maintenance)
          Adaptive Management Strategies (i.e., what happens when routine monitoring or maintenance encounters
            a problem)