Page 51 - _ 180314 Special Yucaipa GSA Packet
P. 51

Table of Contents


                       1.   Infiltration Testing Work Plan Approach .......................................................................... 1
                         1.1.   Investigation Sites and Impacted Waterways ........................................................... 1
                         1.2.   Infiltration Test Methodology ................................................................................... 2

                         1.3.   Site Security and Fencing .......................................................................................... 4
                         1.4.   Traffic Control and Signage ....................................................................................... 4
                         1.5.   Potential Water Sources ........................................................................................... 5

                         1.6.   Water Conveyance and Flow Control System ........................................................... 5
                         1.7.   Infiltration System Monitoring Activities .................................................................. 6
                         1.8.   Groundwater Monitoring Activities .......................................................................... 7

                         1.9.   Best Management Practices ..................................................................................... 7
                       2.   Regulatory Permit Requirements ..................................................................................... 8
                         2.1.   San Bernardino County Flood Control District Requirements .................................. 8

                         2.2.   CDFW Streambed Alteration Agreement .................................................................. 8
                         2.3.   USACE Section 404 Permit for Dredge and Fill Discharges ....................................... 9
                         2.4.   Regional Water Quality Control Board ..................................................................... 9
                       3.   FieldWork Schedule and Cost Estimate .......................................................................... 10

                         3.1.   Fieldwork Schedule ................................................................................................. 10
                         3.2.   Preliminary Cost Estimate ....................................................................................... 10
                       4.   References ...................................................................................................................... 12



                       List of Tables


                       Table 1.      Investigation Site Information Summary



                       List of Figures



                       Figure 1.     Seven SBCFCD Recharge Testing Sites
                       Figure 2.     Six non‐SBCFCD Recharge Testing Sites
                       Figure 3.     Infiltration Test Process Flow Diagram





                        Final Infiltration Test Work Plan for
                        Thirteen Investigation Sites
                        Yucaipa Valley, CA                        ii                  TODD GROUNDWATER