Page 213 - _ 180314 Special Yucaipa GSA Packet
P. 213

From:          Edwin Lin
                 To:            Aaron Jones
                 Cc:            David Drewelow
                 Subject:       Follow-up to questions concerning Yucaipa Recharge Testing Implementation
                 Date:          Thursday, February 8, 2018 5:19:05 PM
                 Attachments:   Todd Groundwater Yucaipa Recahrge Testing - Table 2 Project Budget and Schedule of Fees (revised February 8,
                                2018).pdf


                 Hi Aaron,
                 I’m writing to follow up our discussion on Monday. Specifically, you had questions about the
                 following items:

                    1.  The data collection process, frequency of data recording, and overall field supervision
                    2.  the feasibility of breaking down one test site and setting up at the new test site on the same
                       day

                1.  With respect to data collection system and frequency, the proposed infiltration system includes
                   flowmeter readings tied to the telemetry system, so that real-time instantaneous and totalized
                   flowmeter readings are accessible 24/7. However, the system does not include real-time test
                   basin water levels tied to the telemetry system. While the water levels in the test basins will be
                   controlled within a relatively tight range (+/- 2 feet), we do see a value in having real-time and
                   recorded measurements of water levels to confirm system functionality and to allow for more
                   precise calculation of vertical infiltration rates on a daily basis. David Drewelow has reviewed the
                   changes needed to upgrade the telemetry system to incorporate flowmeter and water level
                   readings and recording of data with a datalogger. The increase in costs for the telemetry upgrade
                   is $780 per test site (or $10,647 for thirteen sites with Todd Groundwater 5% markup) and is
                   recommended for addition to the field program.


                2.  With respect to site-to-site mobilization/demobilization days, I spoke with David Drewelow, and
                   we are comfortable with the proposed costs to perform the earthwork and moving of equipment
                   in one work day. Our costs include field crews being onsite as long as needed to ensure the
                   infiltration system is properly functioning (even if that goes into Tuesday). Using two field crews,
                   the work flow on Mondays would be as follows (1) in the morning, excavate the test basin at the
                   new site and de-mobe equipment at the completed site (and move equipment to the new site
                   with timing it to coincide with completion of excavation at new site), and (2) in the afternoon, fill
                   in test basin at completed site and return site to pre-disturbed grade, and start the test at the
                   new site.
                    We acknowledge that unforeseen conditions/delays could occur at a particular site that could
                    lead to additional work. This could be due to one of the following reasons: (1) difficult excavating
                    conditions, (2) site access issues, (3) increased traffic control measures/requirements, or (4)
                    significant increased hose length from preferred water source to recharge site. For these
                    reasons, I propose to add 10 hours of labor (and travel costs) for Todd Groundwater under Task
                    2: Intra-Site Demobe/Mobe and Testing (Sites 3-13; 11 times). This covers an additional site visit
                    to supervise the first site-to-site mobilization/demobilization. Additionally, we recommend
                    increasing the overall project contingency from the currently proposed 3 percent up to 5
                    percent.
                 I’ve attached a revised cost table that incorporates the items above. As you can see, total estimated


                                  Yucaipa Groundwater Sustainability Agency - March 14, 2018 - Page 188 of 226
   208   209   210   211   212   213   214   215   216   217   218