Page 256 - _ 180314 Special Yucaipa GSA Packet
P. 256

San Bernardino Valley Municipal Water District

                                               INFILTRATION TESTING IMPLEMENTATION FOR THIRTEEN SITES WITH TWO SITES TESTED SIMULTANEOUSLY IN THE YUCAIPA BASIN AREA

                                                                                                                               Yucaipa Basin Recharge Study
                                                                                                                           PROJECT SCHEDULE  - Alternative A

          Task                                                     Description                                                  Mar-18           Apr-18          May-18           Jun-18           Jul-18          Aug-18          Sep-18           Oct-18          Nov-18           Dec-18

             1
           1.1         Project Kick-Off Meeting
           1.2         Finlaize Facilities Design and Develop Process and Instrumentation Diagram

           1.3         Prepare Detailed Site Plan for 13 Sites (submit for review)
           1.4         Progress Meeting and Finalization of Workplan
           1.5         Project Management and Permit Suport

             2
           2.1     a Fabrication of Needed Equipment (Instrumentation only)
                       Conduct Infiltration Testing at 13 Sites (assumes 3-weeks for set-up, testing, and tear-
           2.2
                       down per site)
           2.3         Data Down Load and Testing Oversight
           2.4         Data Compilation Analysis and Draft and Final Report







                                                                                                                                    PROJECT SCHEDULE  - Alternative B
          Task                                                     Description                                                  Mar-18           Apr-18          May-18           Jun-18           Jul-18          Aug-18          Sep-18           Oct-18          Nov-18           Dec-18           Jan-19

             1
           1.1         Project Kick-Off Meeting
           1.2         Finlaize Facilities Design and Develop Process and Instrumentation Diagram

           1.3         Prepare Detailed Site Plan for 13 Sites (submit for review)
           1.4         Progress Meeting and Finalization of Workplan
           1.5         Project Management and Permit Suport

             2
           2.1     b Fabrication of Needed Equipment  - Optional Contanainer System
                       Conduct Infiltration Testing at 13 Sites (assumes 3-weeks for set-up, testing, and tear-
           2.2
                       down per site)
           2.3         Data Down Load and Testing Oversight
           2.4         Data Compilation Analysis and Draft and Final Report




                       GEOSCIENCE Working Period

                       Client Review
                       Winter Hiatus if Required
                       Deliverable Date



                       Meeting / Workshop










                9-Feb-18                                                                                                                                 Page 1 of 1                                                                                                        GEOSCIENCE Support Services, Inc.