San Bernardino Valley Municipal Water District
INFILTRATION TESTING IMPLEMENTATION FOR THIRTEEN SITES WITH TWO SITES TESTED SIMULTANEOUSLY IN THE YUCAIPA BASIN AREA
Yucaipa Basin Recharge Study
PROJECT SCHEDULE - Alternative A
Task Description Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
1
1.1 Project Kick-Off Meeting
1.2 Finlaize Facilities Design and Develop Process and Instrumentation Diagram
1.3 Prepare Detailed Site Plan for 13 Sites (submit for review)
1.4 Progress Meeting and Finalization of Workplan
1.5 Project Management and Permit Suport
2
2.1 a Fabrication of Needed Equipment (Instrumentation only)
Conduct Infiltration Testing at 13 Sites (assumes 3-weeks for set-up, testing, and tear-
2.2
down per site)
2.3 Data Down Load and Testing Oversight
2.4 Data Compilation Analysis and Draft and Final Report
PROJECT SCHEDULE - Alternative B
Task Description Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19
1
1.1 Project Kick-Off Meeting
1.2 Finlaize Facilities Design and Develop Process and Instrumentation Diagram
1.3 Prepare Detailed Site Plan for 13 Sites (submit for review)
1.4 Progress Meeting and Finalization of Workplan
1.5 Project Management and Permit Suport
2
2.1 b Fabrication of Needed Equipment - Optional Contanainer System
Conduct Infiltration Testing at 13 Sites (assumes 3-weeks for set-up, testing, and tear-
2.2
down per site)
2.3 Data Down Load and Testing Oversight
2.4 Data Compilation Analysis and Draft and Final Report
GEOSCIENCE Working Period
Client Review
Winter Hiatus if Required
Deliverable Date
Meeting / Workshop
9-Feb-18 Page 1 of 1 GEOSCIENCE Support Services, Inc.