Page 63 - _ 180314 Special Yucaipa GSA Packet
P. 63

3.     FIELDWORK SCHEDULE AND COST ESTIMATE



                        3.1. FIELDWORK SCHEDULE

                       Proposed Infiltration testing is scheduled to commence in late summer/early Fall of 2017, so
                       that any re‐routing of storm flows in flood control channels and basins would not be
                       required. In order to minimize labor and equipment costs and ensure an efficient work flow,
                       we recommend that initial site preparation (i.e., excavation and installation of conveyance
                       piping, flow controls, fencing, and traffic control) and test initiation be conducted at two
                       investigation sites, staggered one week apart. Site preparation (and demobilization) would
                       occur on Mondays, with test initiation scheduled on Tuesdays. Under this scenario, site
                       preparation and test initiation at Site 1 would occur on Monday and Tuesday of the first
                       week (Week 1). This would be followed by site preparation and test initiation at Site 2 in
                       Week 2. At the beginning of Week 3, testing would be completed at Site 1, and equipment
                       and materials would be moved from Site 1 to Site 3, where testing would begin the same
                       week. At the beginning of Week 4, testing would be completed at Site 2, and equipment and
                       materials from Site 2 would be moved to Site 4, where testing would begin the same week.
                       This process would be repeated as needed to complete infiltration testing for the total
                       number of investigation sites selected for infiltration testing.

                       The proposed field schedule provides the following advantages: (1) the contractor is on a
                       fixed weekly schedule for excavation, equipment mobilization/demobilization and
                       monitoring activities, and (2) materials and labor (including fire hose, manifolds, basin trees,
                       and traffic ramps/signage) are required for exactly two sites throughout the project at any
                       given time.


                       Given this staggered approach, the number of weeks to complete proposed infiltration
                       testing would equal to the number of investigation sites plus one week. Accordingly, if
                       infiltration testing is proposed for thirteen sites, field activities could be completed in 14
                       weeks. Assuming a start date of August 14, 2017, testing would be completed by November
                       20, 2017). The period of testing could be shorter, if testing is conducted at fewer than
                       thirteen sites, or if three infiltration test systems are fabricated and used instead of two
                       systems.

                        3.2. PRELIMINARY COST ESTIMATE


                       Table 2 shows a preliminary cost estimate for performing the infiltration testing at the
                       thirteen investigation sites. Costs for contractor excavation, fencing, installation of water
                       conveyance equipment and materials, weekly monitoring of operation and collection of flow
                       meter data, site demobilization, and intra‐site movement of equipment are included. A
                       detailed breakdown of contractor equipment, rental fees, and labor is provided in Appendix
                       D. Preliminary engineering costs for pre‐field coordination (including permit acquisition
                       support), project management, data analysis and reporting are also included.



                        Final Infiltration Test Work Plan for
                        Thirteen Investigation Sites
                        Yucaipa Valley, CA                          10                  TODD GROUNDWATER

                                  Yucaipa Groundwater Sustainability Agency - March 14, 2018 - Page 62 of 226
   58   59   60   61   62   63   64   65   66   67   68