Table 2. Estimated Project Cost

                                            Items                      Total      Total      Total
                                                                    Engineering   Contractor   Cost
                                                                       Labor      Costs
                           1. Engineering – Pre‐Field Coordination/Permit   $15,000         $15,000
                             Acquisition and Project Management
                           2. Contractor Pre‐Field Work Tasks                      $6,600    $6,600
                           3. Contractor Mobilization, Setup, and Startup         $19,200   $19,200
                             (2 sites)
                           4. Site Visit (weekly; 14 times)                        $9,400    $9,400
                           5. Move Equipment from Existing Site to New           $116,800  $116,800
                             Site (11 times)
                           6. Site Demobilization (13 sites)                      $86,200   $86,200
                           7. Traffic Ramps and Signage                            $6,000    $6,000
                           8. Engineering – Data Analysis and Reporting  $15,000            $15,000
                           Total Costs                               $30,000     $244,200  $274,200
                           Markup Fee on Contractor (10%)                         $24,400
                           Total Costs (with 10% Contractor Markup)  $30,000     $268,600  $298,600
                           Total Costs (with 10% Contractor Markup)                         $23,000
                           Per Site (13 Sites)
                          Notes:
                          1 – fire hose length assumed to be 1,000 feet for all investigation sites. Actual unit cost is $25 per 50‐foot
                          section.
                          2 – traffic ramps to protect fire hose at road crossings estimated at 50 feet per site based on nearest fire
                                                                                               th
                                                                  th
                          hydrant for 4 sites (Wilson Creek III, Yucaipa Creek at 7  Place, Chapman Heights Basin, and 10  Street and
                          Avenue E). Rate is $20 per week per two‐foot section of heavy duty traffic ramp, rating of 25,000 pounds
                          per tire.
                          3 – Traffic signage of $500 per site for 2 weeks added.
                          4 – The following items have not been included in the cost estimate:
                               Cost for test water
                               Water meter rental fee
                               Water tank (21,000 gallon closed steel roll off tank has an estimated delivery charge of $640,
                               estimated pickup charge of $640, and estimated intra‐site move charge of $640).
                               City, county, and state permit fees
                       As shown in the table, the estimated total project cost is estimated at $298,600, equating to
                       approximately $23,000 per site. This preliminary cost estimate does not include costs for
                       test water, water tanks (if needed), hydrant meter rental fees, and associated permit fees.












                        Final Infiltration Test Work Plan for
                        Thirteen Investigation Sites
                        Yucaipa Valley, CA                          11                  TODD GROUNDWATER