Infiltration Test Results















                                                                                                                                  A                                          B






                                                                                                                                                                                                                                         E





                                                                                                                                                                                        A. Traffic control and buried hose from SMWC hydrant
                                                                                                                                                                                        B. Testing in progress (Day 1)
                                                                                                                                                                                        C. EX-4 monitoring well (151' deep)
                                                                                                                                                                             D               located ~100' east of test basin
                                                                                                                                                                                        D. Flow control skid at end of test (Day 14)
                                                                                                                                                                                        E. Test in progress view from east (Day 7)










                                                                                                                                  C
                                                                                                                                                  Conclusions:
                                                                                                                                                  - Results of infiltration testing indicate that the site is suitable for recharge.
                                                                                                                                                  - Full-scale basin initial infiltration rates (based on 50% of measured field-scale testing infiltration
                                                                                                                                                  rates) are estimated at 19.5 feet/day.
                                                                                                                                                  - Long-term infiltration rates (based on 50% of full-scale basin initial infiltration rates) are estimated
                                                                                                                                                  at 9.8 feet/day.
                                                    Test Start  Sep-10-2018                                                                       - Relatively high infiltration rates are representative of the permeable vadose zone sediments
                                                                                                                                                  (sand, gravel) encountered in adjacent exploratory boring EX-4
                                                    Test End   Sep-24-2018
                                                                                                                                                  - No significant fine-grained silt/clay deposits were encountered in EX-4, which was drilled to
                                  Basin Dimensions (L x W) (ft)     29 x 28                                        Wildwood Creek Basin           151 feet-bgs. Depth to water in MW-3 was 103 ft-bgs after 6 days of testing and rose to
                                    Average Water Height (ft)           3.0               South Mesa Barrier       Test Site                      within 99 ft-bgs at the end of testing (after 14 days of infiltration).
                                                           2
                            Infiltrating Area Basin Bottom (ft )       960                                   " )  X Y Boring EX-4                 - While long-term estimates consider expected clogging of the basin bottom from SWP water,
                                                                                                                                                  actual long-term rates will be dependent on the specific site recharge goal and implementation
                                                           2
                     Infiltrating Area Basin Bottom + Walls (ft )    1,270                                           Peizometer PZ-3              of a basin maintenance plan.
                                  Total Water Added (gallons)     4,040,929
                                                                                                                                                  Recommendations:
                                Total Water Added (acre-feet)         12.4
                                                                                                                                                  - Pilot scale infiltration test is recommended to identify potential site vadose zone storage capacity
                                                   High (ft/d)        45.8                                                                        constraints due to recharge mounding and the influence of the South Mesa Barrier.
               Infiltration Rate
                                                   Low (ft/d)         32.2                                                                        - Prior to pilot testing, installation of monitoring well west of the South Mesa Barrier is recommended
              (Constant-Head)                                                                                                                     to confirm groundwater storage benefits from managed aquifer recharge at this location.
                                               Average (ft/d)         39.0
               Infiltration Rate                    High (ft/d)       31.2
                (Falling-Head)                     Low (ft/d)         28.3                   SMWC Hydrant       ยด     0            400 Feet                                                                                Figure 11
                Full-Scale Basin Est. Initial Infiltration Rate (ft/d)  19.5                                                                                                                                           Wildwood Creek
           Full-Scale Basin Est. Long-Term Infiltration Rate (ft/d)     9.8                                                                                                                                                  Basin