December 2016         Preparation Checklist for GSP Submittal Guidance Document


 GSP   Water Code                         Section(s) or
 Regulations   Section   Requirement   Description   Page Number(s)
 Section                                   in the GSP

 Article 5. Plan Contents, Subarticle 5. Projects and Management Actions
 354.44      Projects and   • Description of projects and management actions that will
 Management   help achieve the basin’s sustainability goal
 Actions   • Measureable objective that is expected to benefit from
 each project and management action
 • Circumstances for implementation
 • Public noticing
 • Permitting and regulatory process
 • Time-table for initiation and completion, and the accrual of
 expected benefits
 • Expected benefits and how they will be evaluated
 • How the project or management action will be
 accomplished. If the projects or management actions rely
 on water from outside the jurisdiction of the Agency, an
 explanation of the source and reliability of that water shall
 be included.
 • Legal authority required
 • Estimated costs and plans to meet those costs
 • Management of groundwater extractions and recharge
 354.44(b)(2)   10727.2(d)(3)     • Overdraft mitigation projects and management actions