Workshop Memorandum No. 19-090                                                      Page 3 of 19



                                          YUCAIPA VALLEY WATER DISTRICT
                                          CAPITAL IMPROVEMENT PROGRAM


                 Project     Recycled Water – Wilson Basin Recycled Water Pipeline



                 Division    Recycled Water                           Project Priority        Important

                                                                      Projected Start
                Category     Pipeline Expansion                                                 2019-2
                                                                           Date


                  Phase          Planning             Design           Environmental         Construction


                  Notes


                                  COST BY TYPE                                   FUNDING SOURCE
                Preliminiary Engineering/Design                $ 0   Reserves/Depreciation          $ 700,000
                Environmental                                  $ 0   Development Impact Fees              $ 0
                Right-of-Way/Land Acquisition                  $ 0   Federal Participation                $ 0
                Labor, Equipment, Administration          $ 360,000  State Participation                  $ 0
                Contract Construction                     $ 300,000  Bond Financing                       $ 0
                Construction Engineering                   $ 40,000  Local Matching                       $ 0
                Other: Environmental/Permitting/Misc           $ 0   Other Funds                          $ 0
                                             Total        $ 700,000                    Total        $ 700,000


               Project Description:

               Recycled Water – The Wilson Creek Basin Water Recharge project will enable the District to
               recharge Recycled Water at the Wilson Creek Basin facility.

               The Project would provide additional recharge of the Yucaipa groundwater sub basin by surface
               application of highly treated recycled water from the Wochholz Regional Water Recycling Facility
               (WRWRF) at the Wilson Creek Basins (Basins), as well as surface application of surplus water
               from the State Water Project (SWP) delivered via the SWP East Branch Extension. The Yucaipa
               sub basin is located within the Upper Santa Ana Valley groundwater basin, and currently serves
               as  a  local  source  of  drinking  water  that  is  recharged  by  natural  underflow  from  upgradient
               groundwater sub basins, as well as by deep percolation of precipitation and streambed infiltration.
               The Wilson Creek Basins are currently used to recharge SWP water and have a 7,000-acre feet
               per year recharge capacity. If SWP water is unavailable, additional diluent may be provided by
               applying  potable  water  to  the  Wilson  Creek  Basins  from  the  Yucaipa  Valley  Regional  Water
               Filtration Facility (YVRWFF), located adjacent to the spreading basins. A new pipeline will be
               constructed to convey recycled water from Yucaipa Valley Water District (the District)’s existing
               recycled water distribution system to the Wilson Creek Basins, as well as a new booster pump
               station and up to two monitoring wells.