In addition, all electronic spreadsheet files of data collected in the field will be submitted to
               Valley District in the latest version of Microsoft Excel. GIS maps and associated shapefiles of
               construction boundaries and excavation sites will be submitted in ArcGIS v10.


               Task 4 – Project Management

               This task will cover project administration and communication between Todd Groundwater,
               DRE, Valley District staff, SBVFCD staff, and other project partners for the duration of the
               project. Costs include time by Todd Groundwater to review progress billings by DRE to confirm
               accounting and billing for time and materials used to conduct infiltration testing work at each
               site is accurate.

               Five (5) progress conference calls are included to keep Valley District informed of completed
               activities, preliminary results, and planned field activities. Additionally, two (2) in‐person status
               meetings are included to discuss preliminary findings, proposed testing modifications, and steps
               needed to ensure site and water access at subsequent test sites. While the timing of the status
               meetings can be modified, the first status meeting is proposed following the completion of
               testing at Site 2, and a second status meeting is proposed following completion of testing at
               Site 6.

               Project Team

               Todd Groundwater offers a strong technical team qualified to successfully implement the
               infiltration testing Work Plan. Our team is experienced in several key areas that will benefit this
               project including:

                         Technical expertise with all phases of recharge feasibility evaluation
                         Design, installation, and supervision of multi‐day field data collection programs

                         Innovative and critical thinking for problem solving

               A project organization chart is presented below, followed by a description of the team
               member’s role and relevant experience. A resume for each team member is presented in the
               Appendix.

                                             Project Organization Chart

















               Proposal – SBVMWD Yucaipa Basin Area           4                         TODD GROUNDWATER
               Infiltration Testing of Thirteen Sites                                            January 2018
                                  Yucaipa Groundwater Sustainability Agency - March 14, 2018 - Page 171 of 226
   189   190   191   192   193   194   195   196   197   198   199