Page 220 - _ 180314 Special Yucaipa GSA Packet
P. 220

Project Needs                                          be made either by hand or using a powered trencher to
                                                               accommodate the skirt.
        We have carefully considered the work plan provided in   With this alternative, each container would have an
        the RFP, past data, and our experience at the site and with   infiltration footprint of approximately 280 square feet (36
        other projects. In providing our proposal we have identified   ft x 8 ft). The online instrumentation, cellular SCADA, and
        several key issues that are discussed below. Additionally we   all water inlet controls to the basin would be mounted in
        have prepared and provided cost estimates for two options.   the container, and the container itself would pond water
        The first closely follows the work plan presented in the   above the test area. Water would be supplied from the
        RFP,and the second provides an option for a containerized   hydrant to a connection in the side of the container. Up
        infiltration basin that can potentially reduce costs,   to three containers could be set at a site providing 840
        streamline project permitting, and provide more accurate   sq. ft of percolation area—nearly the size of a 30 x 30 ft.
        data than a 30’ by 30’ infiltration basin.
                                                               pit. If multiple containers are used at a site, containers
                                                               could be spaced at any distance apart to obtain a more
        Containerized Infiltration Basins:                     representative estimate of percolation rates, particularly
        Alternative to Excavated Pits                          in sites with varying conditions. This approach has the
                                                               advantage of:
        We have carefully considered the challenges that excavating
        13, 30 x30 ft temporary pits poses on site security,   1.  A lower overall project cost
        permitting and the overall logistics of your project. In   2.  Potentially more representative data at each
        our costs, we have included an alternative line item for a   percolation site using multiple basins spaced apart
        containerized infiltrometer in lieu of using excavated pits   3.  Potentially more streamlined with respect to obtaining
        for determining infiltration rates. With this approach, a 40   and complying with all permits needed for the project,
        ft x 8 ft shipping container would be modified and used    and
        as a stand-alone infiltration basin (See inset diagram).   4.  Lower risk of vandalism
        The bottom would be removed from the container, and
        a  continuous skirt would be welded around the base    Stockpile Soil Permitting and Safety
        of the container protruding down approximately 18 in.
        The container would be set directly over the test site,   There is a lot of uncertainty surrounding the needed
        which would eliminate the need for excavation. The     BMPs for each site and associated public safety concerns.
        container would be set at each site using either a crane   Specifically, placing unconsolidated soil either around
        or large forklift, and a 4 in. by 18 in. deep trench would   the infiltration pond, or above the storm channel banks




































        Alternate Approach

        The image above illustrates an optional approach that if utilized, could reduce permitting, lower construction costs, reduce the risk
        of vandalism, and potentially provide more representative data. Additionally, the system can be reused and easily transported to
        additional test sites.



                                  Yucaipa Groundwater Sustainability Agency - March 14, 2018 - Page 194 of 226      2
   215   216   217   218   219   220   221   222   223   224   225