Page 222 - _ 180314 Special Yucaipa GSA Packet
P. 222
Project Approach
developed for this project (See Inset Figure Below) we
Based on our past experience in the subbasin, past project anticipate that this will serve all sites that have pressured
work, and review of the RFP and associated work plan, we flow connections. Some modification will be required if
have developed an approach that provides an efficient and testing is conducted using an onsite water storage tank.
robust evaluation of infiltration rates at each site.
1.3 Develop Detailed Site Plan for 13
1.0 Develop Project Work Plan Sites
Prior to equipment mobilization for field testing a project
1.1 Project Kickoff Meeting work plan will be prepared detailing the site specific
We will conduct a meeting with project team members and
partner agencies to review the scope of work, any new data Proposed Process Diagram
acquired, and review project schedules and critical path The diagram below illustrates our proposed instrumentation.
items. We also recommend performing a brief site review This method will simplify the instrumentation needed, and allow
immediately, or shortly before the project kickoff meeting for automated operation and remote control.
to confirm site conditions and refine work plans and access
routes if necessary.
1.2 Finalize Facilities Design
and Develop Process and
Instrumentation Diagram
A final design for the basin inlet along
with all needed water conveyance and
instrumentation will be provided to the
contractor. We will develop a process
and instrumentation diagram calling
out line sizes, materials and connection
types to use as a basis for fabricating
the water inlet manifolds, flow, level
and pressure instrumentation, remote
valve shutoff at fire hydrant and
SCADA data acquisition. For purposes
of preparing costs for this RFP, a
preliminary P&ID has already been
Yucaipa Groundwater Sustainability Agency - March 14, 2018 - Page 196 of 226 4