2.3 Data Download and Testing Oversight
Flowrates and levels in the percolation ponds will be
remotely monitored during testing so that we can keep a
close watch on the infiltration rate trend. With a daily check
on percolation rates from the web-based SCADA portal,
we will be able to better anticipate the end of testing and
provide instruction to the sub-contractor to prepare for de-
mobilization and moving to the next site.
During the initial startup on the first day, we will have
one of our field staff onsite to address any unforeseen
issues. We have budgeted effort for our field technicians
to check in on the site once per week to confirm that the
equipment is operating properly perform a QC check by
measuring level in the pond and cross checking SCADA data
against local totalizers on the magnetic flow meters and
the totalizer on the hydrant meter. We have also budgeted
for the contractor to be on site 1-time during each of the
13 tests as a contingency for unforeseen conditions and/or
equipment maintenance.
2.4 Data Compilation Analysis and
Reporting
We will prepare a comprehensive final report that
documents the field data, test results, and data analyses
for each site. The report will provide an analysis and
recommendations for long-term percolation rates for each
site. We will submit an electronic copy of the draft report
and three (3) hard copies plus an electronic copy (pdf file)
of the final report.
Task 2.0 - Deliverables
We understand the Task 2 deliverables will include:
• Labor and equipment necessary to conduct the field
recharge test developed in the above task to
• achieve a recharge rate in feet per day
• Analysis of data (including site specific recharge curve
for each selected site)
• Preparation of a final report presenting the results,
limitations and recommendations
Yucaipa Groundwater Sustainability Agency - March 14, 2018 - Page 198 of 226 6